|
February 7, 2008
Jacqueline Onciano
Monterey County Planning Department
168 West Alisal St., Second Floor
Salinas, CA 93901-2487
SUBJECT: COMMENTS
ON DEIR FOR RANCHO CANADA VILLAGE SPECIFIC PLAN
Dear Ms. Onciano:
LandWatch Monterey County has reviewed the DEIR for the proposed
Rancho Canada Village, a large subdivision that would significantly
impact Carmel Valley both during the construction phase and after
completion. The approximately 300-unit subdivision would be built
in the floodway and/or flood plain of the Carmel River; it entails
the use of 200,000 cubic years of fill in and around the Carmel
River floodway; and it would be constructed immediately next door
to Carmel Middle School (CMS). Given the extent of these impacts,
it is critical that the DEIR accurately detail and analyze the
various environmental impacts.
We are disappointed with the generally poor quality of this DEIR.
For example, both flooding and air quality impacts on the school
children at CMS – centrally important issues – are
poorly addressed in the DEIR. In the absence of high quality analysis,
neither Monterey County nor the citizens of Carmel Valley can truly
make an informed decision on the merits of this project.
The following are our specific comments on the DEIR:
- Project Description (ES-3 and 2-2) identifies
the following: 281-mixed-use residential units (182 single family homes, 64
townhomes and 35 condos) with140 deed-restricted for Affordable
and Workforce housing; 2.5 acres of parks; 39 acres of permanent
open space; construction of a levee; movement/placement
of 200,000 cu. yd. of fill; and extension of Rio Road into the
proposed project. The description does not include the
following:
a. A
potential of 28 carriage houses identified (pp. 4 & 9) of the
Community Patterns Book. These units are excluded from all
impact analyses.
b. Location
of the 200,000 cu.yds. of fill to be imported and/or moved on site.
- Development in Floodway. The DEIR states (p. ES-3) the
project requires a use permit for building in the floodway. Later
the DEIR states (p. ES-5) the project would be within the
100-year floodplain (but not in the floodway). This discrepancy
should be addressed.
- Water Rights. The DEIR indicates (pp. ES-6 and 2-9)
the applicant’s water rights have been confirmed and the
project would use less water than current demand. The text
(p. 2-9) suggests the applicant would retain water rights not
allocated for the project, i.e., “Water would be supplied
to the homes either through the Cal-Am distribution system by
assigning a portion of Rancho Canada’s water rights to
Cal-Am..." (Emphasis
added). Thus, while the project itself may not require
the same amount of water as existing uses, the “saved" water
would remain available to be used by Rancho Canada at its discretion.
- Envirornmentally
Superior Alternative. The DEIR identifies
the Environmentally Superior Alternative as the Medium-Density
Alternative (p. ES-15) because it would have somewhat lessened
aesthetic impact and substantially less indirect effect on traffic
generation. Then the DEIR states for Carmel Valley as a
whole, cumulatively the Medium-Density Alternative would not
be environmentally superior. An alternative that mitigates
project level and cumulative impacts and is, in fact, an Environmentally
Superior Alternative, should be identified and analyzed pursuant
to CEQA Guidelines.
- Urban Runoff. P. 2-10 states that the MCWRA has an unwritten
policy that requires post-project, 100-year flow rate not to
exceed the pre-project, 10-year flow rate. The DEIR finds
this policy impractical which apparently means that the policy
would not be met. Policy 3.1.1.2 of the CVMP includes a
provision “... for slow release of runoff water so that
runoff rates after development do not exceed rates prevailing
before development...". While the Consistency
Analysis (Appendix C) finds the project consistent with this
policy, it concludes, “As described in Chapter 3.2 of the
draft EIR, the Project would not comply with specific runoff
retention requirements of the County; however, due to the location
of the Project in the lower part of the basin and the drainage
design of the Project, discharge of runoff from the site would
not result in increased peak discharge in the Carmel River." Further,
the DEIR states (p. 3.3-29), “In addition, the increase
in impervious surface upon completion of the proposed development
could result in increased runoff into the Carmel River..."On
p. 3.2-20, it is estimates that 15% of stormwater runoff from
Drainage Area 27 will not be contained onsite during storm events. The
DEIR states (p. 3.2-27), “These assumptions lead to an
estimated annual total runoff and recharge of 34.9 acre-feet
for pre-project conditions, with much of this volume going to
recharge. This value is only 1.7 acre-feet greater than
the estimated recharge of 33.2 acre-feet for post-project conditions
estimated by Balance Hydrologics." Based on
these findings, the project should be found to be inconsistent
with Policy 3.1.1.2. Further, it should be found
that the project’s impact on stormwater runoff is significant
and unavoidable.
- NPDES Permit. P. 3.2-14 indicates the project
would require an individual NPDES permit for brine disposal.
The FEIR should indicate the source of brine.
- Mitigation HYD-8
(p. 3.2-29) would require protecting the eastern slope of the
excavated basin with rock or some similar hard substrate. The
impacts of the mitigation measure on aesthetics, riparian habitat,
etc. should be identified.
- Mitigation HYD-9 (p. 3.2-29) would
replace the existing unconsolidated berm at the western edge
of the project area with a floodwall or reinforce the berm
to withstand erosion. The DEIR finds
these measures would ensure that the existing structure’s
current level of protection would be unaffected by any redirection
of flow caused by the project. However, the measure
notes that before any improvements are placed, hydraulic modeling
would need to be done to ensure that improvements would not increase
flooding. This study should be done prior to a finding
that impacts on redirection of river flows would be reduced to
less than significant.
- Project Impact Upstream. Residents living upstream near
Via Mallorca have contended that since the construction of the
existing golf course, upstream flooding has increased. The
DEIR should address the potential impact of the project on upstream
residents in this area.
- Source of 100,000 cu. yds. of Fill. The DEIR indicates
that 100,000 cu. yds. of fill would be imported. We assume
the remaining 100,000 cu. yds. would come from on-site. The
Biological Resources Section should clearly identify the source
of the on-site fill and impacts on biological resources in that
area.
- Mitigation Measure BIO-12 (p.3.3-40) would require the applicant
to retain a qualified biologists. Mitigation Measures BIO-17
to 24 would require the County to retain a qualified biologist. The
reason for change in responsibility from the applicant to the
County should be addressed.
- Scenic Road Status of Carmel Valley
Road. The DEIR incorrectly
refers to Carmel Valley Road as a “proposed" scenic
route rather than a designated scenic route. The report
finds the development would be partially visible from the road
yet concludes this would be a less than significant impact. We
disagree with this finding.
- Impact of Project on Viewshed. The DEIR does not address
whether or not the project would block or interfere with forested
hills and ridges in the background. This analysis should
be undertaken.
- Project Consistency with CVMP Land Use
Designation. The
DEIR finds that the project’s inconsistency with several
policies in the CVMP is insignificant because the project would
require a change in land use designations and zoning, thus making
it consistent, i.e., “Thus, with the adoption of the appropriate
land use designations and zoning, the Specific Plan is considered
to have less than significant impacts related to land use" (p.
3.5-12). This finding is illogical and unsupportable.
- Project
Consistency with Ordinance 3310. The DEIR finds
(p. 3.5-13) the project is anticipated to result in an overall
savings in water use consistent with Ordinance 3310. This
finding cannot be made unless the unused water rights are returned
to the State.
- Mitigation Measure TR-1 calls for contribution toward
the cost of signalization at Laureles Grade and Carmel Valley
Road. Although
this project is included in the Carmel Valley Master Plan Traffic
Study, the project has not been approved and is not scheduled
for construction. Further, the CVMP does not provide for
signalization at this intersection; rather, it calls for other
improvements. Thus, the mitigation measure is inconsistent
with the CVMP.
- Rio Road Connection. The project includes construction
of a road connecting the project to Rio Road. The DEIR
does not address impacts of this project on the environment.
- Air
Quality Data. Data for ozone and PM10 violations
should be updated to 2006 (p. 3.8-8).
- Current AQMP. The most current Air Quality Management
Plan is the 2004 AQMP, not the 2000 referenced in the report
(p. 3.8-12). Project consistency with the most recent plan
to attain PM10 standards should also be addressed. Reference
is also made on this page to 150 lbs/day as the thresholds of
significance for ROG and NOx emissions. The threshold
for both pollutants is 137 lbs/day (MBUAPCD CEQA Air Quality
Guidelines, 2004).
- CO2 Threshold. Reference to 550
lbs/day of CO2 as the threshold of significance (pp. 3.8-14 and
3-8-17) should be qualified to indicate that this only applies
to stationary sources and not mobile sources.
- Construction Emissions. Emissions are described in Table
3.8-6. They were estimated using URBEMIS2007 which requires
data on the duration of construction activity. Since the
DEIR indicates (p. 3.8-19) that it is unknown how long construction
activities would occur, the input assumes a “typical" construction
period “not lasting more than several months in duration...". Because
the data in Table 3.8-6 do not reflect construction emissions
for this project, they cannot be relied upon for an evaluation
of the impacts of the project on air quality. The air quality
analysis should be revised based on an accurate and complete
project description.
- Haul Truck Emissions. Emission estimates for construction
activity (Table 3.8-6) exclude emissions from the 7,200 trucks
needed to haul 100,000 cu. yds. of fill and emissions from hauling
or moving the other 100,000 cu. yds. of fill. The Traffic
Report (Appendix D, p. 40) indicates that the grading schedule
for importing 100,000 cu. yds, of fill would be done over 28
working days for a total of 257 trips per day and 58 trips/hour. Using
a standard NOx emission factor (0.03 lbs/mile) and assuming a
20 mile round trip (the source of fill is no where identified
in the DEIR), haul trucks alone would generate 154 lbs per day,
58 lbs in excess of the estimates for all construction activities
identified in Table 3.8-6. Further, the URBEMIS 2007 input
for construction emissions (Updated Air Quality Analysis Report)
assumes 199.6 VMT for on-road truck travel, significantly below
the travel for the 257 trips per day identified in the traffic
report.
Estimates for ozone precursor emissions (ROG and NOx)
should be provided for travel to and from the site, idling and
movement on-site. These
emissions should be added to other ozone precursor emissions that
would occur simultaneously and compared to the thresholds of significance
to determine their impacts. Mitigation Measure AIR-3 for
ozone precursor emissions includes a provision to undertake the
project during non-ozone season (May through October), but this
measure would not be undertaken if it were found to be infeasible.
Since November through April (the non-ozone season) is the rainy
season, construction during this period could make the measure
infeasible. Further, depending on a risk assessment discussed
below, it may be necessary to undertake construction during summer
months when students are not in attendance at the Carmel Middle
School. Therefore, there is no assurance that the proposed
mitigation measure would be implemented nor that impacts on regional
ozone levels would be reduced to less than significant.
PM10 emissions
related to filling and emptying the vehicles used to transport
100,000 cu.yds. of fill should be estimated along with emissions
related to movement of the fill on-site. These
emissions should be added to other construction particulate emissions
that would occur simultaneously. Dispersion modeling should
be undertaken to address their impact on public health. Input
into the dispersion model requires data on the distance of the
activity from sensitive receptors; however, those data are currently
unknown (p. 3.8-20). Before an adequate air quality
analysis can be completed, a more detailed project description
must be provided.
Diesel exhaust emissions should be calculated
for haul truck travel, idling and movement on-site. Since
the mitigation measures to address the impacts of diesel exhaust
(AIR-3) may not be feasible as discussed below, a risk assessment
should be completed for diesel particulates and acrolein emissions. The
latter emissions are extremely harmful to adults and children with
asthma. Particular
focus should be given to exposure of children and adults at the
Carmel Middle School and adjacent neighbors.
- On-site Construction
Emissions. Even though the DEIR
states (p 3.8-19) construction duration and distance from sensitive
receptors are unknown, it nevertheless concludes that Mitigation
Measure AIR-3 would reduce impacts from diesel exhaust to less
than significant. AIR-3 identifies a list of technological
and other measures to address impacts of diesel exhaust from
on-site construction activity on local residents and school
children at the Carmel Middle School. The measure states, “The
County shall require the construction contractor to implement
all applicable and feasible control measures required by the
MBUAPCD. This
requirement shall be incorporated into the construction contract....".
First,
MBUAPCD does not regulate construction equipment. Second,
implementation depends on the applicability and feasibility of
the various controls. This uncertainty does not assure that
diesel exhaust emissions would remain at safe levels. Third,
it is unclear which of the controls would be applied to which pieces
of equipment. If all diesel powered equipment had particulate
filters which reduce diesel particulates by at least 85% and acrolein
emissions by 90% and used bio-diesel fuel, impacts would likely
remain at safe levels. However, if only bio-diesel fuel were
used, acrolein emissions would be reduced by only 45% which means
that health risks could be significant depending on equipment used,
duration of use and distance of use from sensitive receptors. Further,
bio-diesel fuel is in short supply, and its availability cannot
be assured. If the County recommends use of best available
control technology for haul trucks to control diesel emissions,
the mitigation measure should address the feasibility of enforcing
the measure for a haul truck fleet that may have numerous owners
and drivers.
In summary, the overall analysis of the impact of construction
emissions on air quality is inadequate for the following reasons:
1.
The duration of construction activity is unknown.
2. The
distance of construction activity from sensitive receptors is unknown.
3.
These data are needed to prepare a dispersion model for particulate
emissions and risk assessments for diesel particulates and acrolein
emissions.
4. Emissions
from haul trucks to be used to transport 100,000 cu. yds of fill
are excluded from the analysis.
- Water Demand. Rancho Canada has water rights for 700AF
(p. 3.10–7). The golf courses use between 309 and 684 AFY
with the existing use on the project site at 138 AFY. The
project water demand is estimated at 120.7 AFY representing a
net reduction in water use of 12 to 17 AFY. The DEIR recommends
that 131 AF be permanently dedicated to the proposed project
leaving 7 AFY for other uses. Because the projected net
water use is reduced to less than current use, the project is
found to not have a significant impact on water supply. This
finding fails to account for the “unused" water that
could be used for other projects. Unless the unused
water is returned to the State, the proposed finding should be
revised accordingly.
- Cultural Resources. Because the project would require
a General Plan Amendment, under State law the County is required
to consult with the applicable Native American Indian Tribe. The
DEIR does not indicate such a consultation has occurred.
- Population. The DEIR should identify the
2004 population forecast for Carmel Valley. AMBAG’s
forecasts show a declining population for the Carmel Valley TAZ
from 10,282 persons in 2005 to 9,849 persons in 2020. Inconsistency
of the proposed project with these forecasts should be addressed
particularly as it relates to AMBAG’s transportation model.
- Development
Potential Under CVMP Cap. All references
to the development potential under the CVMP cap of 1,310 units
should be revised to reflect the errata distributed by the
County at the end of January.
- Greenhouse Bas Emissions. The project would emit about
4,815 tons per year of Greenhouse Gases. Under AB32, Greenhouse
Gas emissions are required to be reduced to 1990 levels
by 2020. Because the project would reduce emissions to
less than what they could be with another design and because
controls to meet AB32 have yet to be implemented, the DEIR finds
that the project is consistent with AB32 and presumably would
not have a significant impact on global warming. While
the DEIR extols the virtue of project design contending that
certain design features would reduce vehicular use, the project
is located over 1/2 mile from shopping and other services - a
distance that exceeds typical pedestrian use. (Indeed, the distance
from the midpoint of the project planning area is more than a
mile from the nearest full-service grocery.) The project would
make it even more difficult for the County to meet a 1990 target
and should be found to have a significant impact on global warming.
- Cumulative Water Demand (p. 4-25). This section bases
its finding on the project’s decreased water use compared
to existing use, failing to note that the unused water increment
would be available for other uses.
Appendix C - CVMP POLICY
CONSISTENCY ANALYSIS
A. 6.1.3
Beneficial uses of water and 6.1.4 Management of Carmel River water
The
project is found consistent because it would result in a decrease
in water demand. A consistency finding must depend
on the applicant’s return of unused water rights to the State;
otherwise, the water could be used for other projects.
B. 7.1.3
Project sited to protect riparian vegetation.
The project
is found consistent. It is unclear if the
proposed finding accounts for impacts on the area which would be
the source of 100,000 cu. yds. of on-site fill.
C. 16.2.6.1
Flood control include restoration of river.
The DEIR does not address
restoration of the river bank east of the project near the Hacienda
homes.
D. 26.1.21
Maintain rural character
The project is found to be consistent with
this policy. Two
hundred and eighty-one units at the proposed density regardless
of whether or not it is visible is not rural.
E. 26.1.23
Open spaces to be located to maintain distinction between more
rural and more suburban areas of valley.
The proposed finding states
that because of the habitat reserve and the existing golf course,
this open space would create a buffer between the project and the
remainder of the Valley. The
finding ignores the existing buffer between development at the
mouth of the Valley and the project. The reasoning
provided in the proposed findings would allow suburban uses all
the way down the Valley, i.e., urban sprawl.
F. 39.1.6
Construction of Hatton Canyon Freeway - “If the Freeway has
not been built, the Board shall limit further development until
the freeway is under construction."
The
project is found to be consistent with this policy. It is
not.
Thank you for the opportunity to review the document.
Sincerely,
Chris Fitz, Executive Director
LandWatch Monterey County
[Return
to Carmel Valley Issues and Actions]
02.06.08
|